Project progress is determined by many factors. This timeline is updated to reflect approvals and gates in the relevant project plan.
Training Committee approved on 12th June. Moving to implementation phase- release date 2nd July.
Two pilots for HV Cable Pulling module completed in May.
Final pilot for HV Operations module completed 6th- 8th May at RelyOn UK. Very positive feedback with only minor amendments proposed to the draft standard.
This project aims to develop and implement a high voltage standard in the wind industry to address skilled labor shortages, enhance safety, and streamline upskilling.