Project progress is determined by many factors. This timeline is updated to reflect approvals and gates in the relevant project plan.
Gate 3 delayed. Training Committee asked for a further analysis of uptake and demand. Moved to 11 September.
Design report with Training Committee for approval today. Following approval, Public Hearing planned for September, piloting end of September/October, final release gate November. Release December.
Re-grouping with the working group now Operations & Cable Pulling modules completed. Analysis to the Training Committee in August. Release planned for December.
This project aims to develop and implement a high voltage standard in the wind industry to address skilled labour shortages, enhance safety and streamline upskilling.